Finally, after some three weeks delay due to inspection failures, there’s some more progress at our new home.
We were told of an issue with the height inspection, presumably related to possible flood – but strange since our home is if anything a couple feet higher than the ones either side, that apparently had no issue! It’s also clear that part of the rear support wall had to be re-constructed (some sort of issue between the design drawings and the actual construction, apparently).
But now, Lennar are “full blast”, allocating two framing crews, so they can try and catch up our home to the rest of the row!